摘要:
A system tool merges different load forecasts for power grid centers. A plurality of load forecast engines are coupled to a load forecast interface and a relational data base that saves load forecast engine data as an input through the load forecast interface. A comprehensive operating plan is coupled to the load forecast engines and the relational database. The comprehensive operating plan is configured to integrate individual load forecasts into a composite load forecast to present a comprehensive, synchronized and harmonized load forecast. A program interface provides access to the composite load forecasting schedule.
摘要:
A method is provided for merging different load forecasts for power grid centers. Area load forecasts are accepted from load forecast engines. A relational database saves load forecast engine data. A comprehensive operating plan integrates individual load forecasts into a composite load forecast to present a comprehensive, synchronized and harmonized load forecast.
摘要:
A system tool merges different load forecasts for power grid centers. A plurality of load forecast engines are coupled to a load forecast interface and a relational data base that saves load forecast engine data as an input through the load forecast interface. A comprehensive operating plan is coupled to the load forecast engines and the relational database. The comprehensive operating plan is configured to integrate individual load forecasts into a composite load forecast to present a comprehensive, synchronized and harmonized load forecast. A program interface provides access to the composite load forecasting schedule.
摘要:
A method is provided for merging different load forecasts for power grid centers. Area load forecasts are accepted from load forecast engines. A relational database saves load forecast engine data. A comprehensive operating plan integrates individual load forecasts into a composite load forecast to present a comprehensive, synchronized and harmonized load forecast.
摘要:
A method is provided for evaluating operational and financial performance for dispatchers in power grid control centers associated with utility systems. A comprehensive operating plan is provided that applies after the fact analysis for performance metrics, root-cause impacts and process re-engineering. after the fact analysis of past events and practices is performed. Actual system and resource conditions are captured. the system and resource conditions are supplied to a relational database. A scheduler engine receives the actual system and resource conditions from the relational database and processes it to calculate system performance. At least one of the following is displayed, transmission evaluation application displays, reference and scenario cases and associations between them, results presented with a graphical or tabular displays, comparison results between scenario cases and a reference case, a family of curves where each curve is a performance metric, comparison of scenario input data, study results and statistical analysis and historical data.
摘要:
A method is provided that enables dispatchers in power grid control centers to manage changes by applying multi-interval dispatch. A multi-stage resource scheduling engine and a comprehensive operating plan are used. Multiple system parameter scenarios are coordinated.
摘要:
A system tool that provides dispatchers in power grid control centers with a capability to manage changes. Included is a user interface and a plurality of scheduler engines. Each scheduler engine is configured to look ahead at different time frames to forecast system conditions and alter generation patterns within the different time frames. A comprehensive operating plan holds schedules generated by the plurality of scheduler engines. A relational database is coupled to the comprehensive operating plan. Input data is initially received from the relational database for each scheduling engine, and thereafter the relational database receives data from the scheduling engines relative to forecast system conditions.
摘要:
A decision-support tool is provided to evaluate operational and financial performance for dispatchers in power grid control centers associated with utility systems. A scheduler engine is coupled to a comprehensive operating plan that applies after the fact analysis for performance metrics, root-cause impacts and process re-engineering. A relational database is coupled to a data archiver that captures actual system and resource conditions and then supplies the system and resource conditions to the relational database. The scheduler engine receives the actual system and resource conditions from the relational database and processes it to calculate system performance. A user interface is configured to display at least one of, transmission evaluation application displays, reference and scenario cases and associations between them, results presented with a graphical or tabular displays, comparison results between scenario cases and a reference case, a family of curves where each curve is a performance metric, comparison of scenario input data, study results and statistical analysis and historical data.
摘要:
A system tool provides dispatchers in power grid control centers with a capability to manage changes. A user interface and a plurality of scheduler engines are provided. A comprehensive operating plan has multiple dispatch engines that are security constrained unit commitments and economic dispatch sequences with different look-ahead periods. The comprehensive operating plan is configured to integrate the dispatch engines into a unified scheduling system. The comprehensive operating plan has a data structure for capturing scheduling data, transaction scheduling, load forecast and time series data. The comprehensive operating plan is configured to coordinate scheduling data to and from power grid system applications and present a comprehensive, synchronized and harmonized view of scheduling data to at least one of, applications, power grid system operators and other stakeholders for power grid system operations.
摘要:
A method is provided for evaluating operational and financial performance for dispatchers in power grid control centers associated with utility systems. A comprehensive operating plan is provided that applies after the fact analysis for performance metrics, root-cause impacts and process re-engineering. after the fact analysis of past events and practices is performed. Actual system and resource conditions are captured. the system and resource conditions are supplied to a relational database. A scheduler engine receives the actual system and resource conditions from the relational database and processes it to calculate system performance. At least one of the following is displayed, transmission evaluation application displays, reference and scenario cases and associations between them, results presented with a graphical or tabular displays, comparison results between scenario cases and a reference case, a family of curves where each curve is a performance metric, comparison of scenario input data, study results and statistical analysis and historical data.