公开(公告)号:US20110273129A1
公开(公告)日:2011-11-10
申请号:US12773504
申请日:2010-05-04
申请人: Carlos James Coe , Aeron Neils Hurst , Mark Isaac Hardin , Matthew Clayton Such , Richard Thomas Jennings
发明人: Carlos James Coe , Aeron Neils Hurst , Mark Isaac Hardin , Matthew Clayton Such , Richard Thomas Jennings
IPC分类号: H02J7/00
CPC分类号: H02J7/007 , G05B15/02 , H02J3/32 , H02J3/382 , H02J3/383 , H02J3/386 , Y02E10/563 , Y02E10/566 , Y02E10/763 , Y10T307/516 , Y10T307/527 , Y10T307/625
摘要: A power delivery rate from a renewable power source to a load is managed by determining, by processing circuitry, a change in a power generation rate, determining, by the processing circuitry, whether the change in the power generation rate exceeds a limit, and then, adjusting, by control circuitry, a power transfer rate to or from a power storage device, such that the adjusting is sufficient to prevent the power delivery rate from exceeding the limit.
摘要翻译: 通过处理电路确定发电速率的变化,通过处理电路确定发电率的变化是否超过限制来管理从可再生电源到负载的电力传送速率,然后 ,通过控制电路调整到或从蓄电装置的电力传送速率,使得调节足以防止电力传送速率超过限制。
-
公开(公告)号:US20130278203A1
公开(公告)日:2013-10-24
申请号:US13924888
申请日:2013-06-24
申请人: Carlos James Coe , Aeron Neils Hurst , Mark Isaac Hardin , Matthew Clayton Such , Richard Thomas Jennings
发明人: Carlos James Coe , Aeron Neils Hurst , Mark Isaac Hardin , Matthew Clayton Such , Richard Thomas Jennings
IPC分类号: H02J7/00
CPC分类号: H02J7/007 , G05B15/02 , H02J3/32 , H02J3/382 , H02J3/383 , H02J3/386 , Y02E10/563 , Y02E10/566 , Y02E10/763 , Y10T307/516 , Y10T307/527 , Y10T307/625
摘要: A power delivery rate from a renewable power source to a load is managed by determining, by processing circuitry, a change in a power generation rate, determining, by the processing circuitry, whether the change in the power generation rate exceeds a limit, and then, adjusting, by control circuitry, a power transfer rate to or from a power storage device, such that the adjusting is sufficient to prevent the power delivery rate from exceeding the limit.
摘要翻译: 通过处理电路确定发电速率的变化,通过处理电路确定发电率的变化是否超过限制来管理从可再生电源到负载的电力传送速率,然后 ,通过控制电路调整到或从蓄电装置的电力传送速率,使得调节足以防止电力传送速率超过限制。
-
公开(公告)号:US08471520B2
公开(公告)日:2013-06-25
申请号:US12773504
申请日:2010-05-04
申请人: Carlos James Coe , Aeron Neils Hurst , Mark Isaac Hardin , Matthew Clayton Such , Richard Thomas Jennings
发明人: Carlos James Coe , Aeron Neils Hurst , Mark Isaac Hardin , Matthew Clayton Such , Richard Thomas Jennings
CPC分类号: H02J7/007 , G05B15/02 , H02J3/32 , H02J3/382 , H02J3/383 , H02J3/386 , Y02E10/563 , Y02E10/566 , Y02E10/763 , Y10T307/516 , Y10T307/527 , Y10T307/625
摘要: A power delivery rate from a renewable power source to a load is managed by determining, by processing circuitry, a change in a power generation rate, determining, by the processing circuitry, whether the change in the power generation rate exceeds a limit, and then, adjusting, by control circuitry, a power transfer rate to or from a power storage device, such that the adjusting is sufficient to prevent the power delivery rate from exceeding the limit.
-
公开(公告)号:US20140183961A1
公开(公告)日:2014-07-03
申请号:US13729801
申请日:2012-12-28
IPC分类号: H02J3/28
CPC分类号: H02J3/28 , H02J3/06 , H02J3/32 , H02J2003/001
摘要: A control system for an energy storage device is coupled to sensors on an electrical grid. The control system is configured to receive a measurement from each of the sensors. The control system determines, based on the received measurements, whether a grid event is a local event or a distributed event. The control system selects a response mode for controlling the energy storage device based on whether the grid event is determined to be a local event or a distributed event.
摘要翻译: 用于能量存储装置的控制系统耦合到电网上的传感器。 控制系统被配置为从每个传感器接收测量。 控制系统基于接收到的测量来确定网格事件是本地事件还是分布式事件。 控制系统基于网格事件是否被确定为本地事件或分布式事件来选择用于控制能量存储设备的响应模式。
-
-
-