Invention Application
- Patent Title: PRIORITIZATION OF POWER GENERATION IN A POWER PLANT COMPRISING WIND TURBINE GENERATORS
-
Application No.: US17787527Application Date: 2020-12-16
-
Publication No.: US20220385065A1Publication Date: 2022-12-01
- Inventor: Mu WEI , Mads Rajczyk SKJELMOSE
- Applicant: VESTAS WIND SYSTEMS A/S
- Applicant Address: DK Aarhus N.
- Assignee: VESTAS WIND SYSTEMS A/S
- Current Assignee: VESTAS WIND SYSTEMS A/S
- Current Assignee Address: DK Aarhus N.
- Priority: DKPA201970830 20191220
- International Application: PCT/DK2020/050371 WO 20201216
- Main IPC: H02J3/00
- IPC: H02J3/00 ; H02J3/38

Abstract:
The invention relates to a method for controlling power generation from a power plant which comprises a plurality of power generating units. The method involves setting a maximal allowed power production for each power generating unit in a selection of one or more power generating units of second priority to a non-zero value, where the maximal allowed power production is determined dependent on whether a first power production gap is greater or less than zero and dependent on a comparison of the first power production gap with a second available power production capability of the selection of the one or more power generating units of the second priority.
Public/Granted literature
- US1702995A Duplex camera Public/Granted day:1929-02-19
Information query