Portland cement concrete slab-on-ground fabrication method for performance satisfaction and reduced carbon emission
摘要:
A ground site for a building is prepared for construction of a portland cement concrete slab-on-grade (PCC SoG). Using a computerized weather application, weather conditions for a geographic locale that includes the ground site are monitored to identify a window-of-time during which the weather application indicates there is a less than 50% chance of precipitation at the geographic locale. The surface of the ground site is proof rolled during the window-of-time. Using concrete emplacement equipment during the window-of-time and only after the ground site passes proof rolling, wet concrete is emplaced on the ground site to a nominal thickness that does not exceed 7 inches and that is at least one inch less than a PCC SoG design for the ground site having a design thickness based on design guidelines set forth by the American Concrete Institute. Emplacing must be completed with at least 4 hours remaining in the window-of-time.